Click to Home
Go To Search


bidsnew.jpg
minutes.jpg
pftv.jpg
employmentrev.jpg
paymentsnew.jpg
pfreshwaternew.jpg
 
Kelly Lane Widening Project
 Kelly Lane Aerial
Project Overview/
Roadway Benefits
Traffic Routes
& Project Updates
FAQ'S   Maps and Visuals




The City of Pflugerville began Phase 1 of the Kelly Lane Roadway Widening Project in December 2013 to help alleviate the traffic congestion along the road, thus allowing an additional 4000 vehicles per day on Kelly Lane, enhance regional and local mobility and connectivity, relieve congestion and increase safety with deceleration lanes and sidewalks.  

January 6, 2015
In December, the city completed the final paving of Phase 1 of the Kelly Lane Roadway Widening Project. Remaining items to be constructed prior to removal of all temporary traffic controls are final striping, guardrail installation (from Benning to Kennemer on north side), powering/testing and operation of new traffic signals and minor pedestrian improvement completion.  

The outside lanes will remained coned off to allow the contractor a space to work to complete the above items. When these final tasks are complete, anticipate the construction barrels removed and the full roadway section open.  All mentioned improvements are anticipated to be completed the month of January (weather permitting) in accordance with the overall project schedule.  

With more than $5.5 million in investments to the road, the Kelly Lane Widening Project has added a 4-lane divided roadway section, dedicated left turn lanes as street intersections and right-turn lanes at Kennemer and Falcon Pointe Boulevard, curb and gutter inlets and installation of new traffic signals. The improvements are estimated to ease congestion by allowing an additional 4000 cars per day on the road. The roadway project nears completion!

December 18
Paving has begun (11 a.m.) and Kennemer intersection is closed. Work will continue until approx 5 p.m. No work on Friday, Dec 19. Anything left unfinished after today will be done on Saturday, Dec 20 to finish up. December 17 - Paving and intersection closures will not occur today (Dec.17) due to temperature and rain possibility, but will resume Thursday, Dec. 18. The intersection of Kelly/Kennemer will have intermediate closures on Thursday but will be fully open by the end of the day. (5 p.m.) December 16 update: Many parents have asked about the crosswalks and child pickup after school. Since the road will be closed at the intersection of Kelly/Kennemer intermittently to allow for paving, it's better to walk to school as all crosswalks will be open for pedestrian traffic throughout the day. Vehicular traffic causes congestion because during parts of Dec 16-17 the intersection of Kennemer and Kelly will be closed to vehicles. The goal is to get the paving done as quickly and effectively as possible and then as soon as the city can open the intersection to vehicles we will. We hope to have the road open for the rush-hour commute, but it is project and weather permitting. Thank you for having patience with us as we are working for you!