NTCMUD#5 Water Distribution Phase 1
Project Information
n conjunction with a series of projects in coordination with Manville Water Supply Corporation, this project will connect the City’s water system to the former North Travis County MUD #5 water system allowing the City to provide water and retail water service to the former North Travis County MUD #5 service area. The scope of work includes construction of approximately 6,883 linear feet (LF) of 24” water main, 710 LF of 16” water main, 100 LF of 12” water main and 1,550 LF of 8” water main along portions of Pflugerville Parkway, Wilke Ridge Lane, Heatherwilde Blvd. and in the Royal Pointe subdivision. 

Project Engineer: Lockwood, Andrews & Newnam, Inc.

Construction Contractor: Prota Construction Inc. & Prota Inc, JV

 To view this project on the city's GIS Map, select Project 23.

Benefits include:
  • Better water transmission capacity and system reliability in the NTCMUD area to serve our water customers
  • Increased capacity for existing and proposed development 
  • Improved water pressure in the area
  • Provides for a needed secondary water connections for overall water distribution

Project Schedule and Status
NTCMUD Phase 1 - May.png
The City Council awarded a construction contract to Prota Construction Inc. & Prota Inc, JV at the April 20, 2015 City Council meeting. City staff anticipate construction to be completed by Spring 2016.

For More Information
For a full list of Capital Improvement Projects, information on potential closures and project updates visit  Sign up for the city's weekly e-newsletter, the Key to the City at