Weiss Lane Roadway Improvements
Project Open House October 26 
Time: 5:30 p.m. – 7:30 p.m.

The City of Pflugerville and Travis County will host an open house at the Pflugerville Justice Center, 1611 E. Pfennig Ln. on Wednesday, October 26 to provide information about the much-anticipated Weiss Lane Roadway Improvements project that is slated to begin in early 2017.  

This project is funded by voter-approved bond funds (City of Pflugerville and Travis County) and will widen the roadway from Wilbarger Creek to Cele Rd. from two lanes to four lanes with curb and gutter and drainage improvements. The southernmost section from Wilbarger Creek to East Pecan St. will be reconstructed as a two-lane roadway with shoulders. The project limits are from East Pecan St. to Cele Rd. (3 miles) and include reconstruction of all bridges from Pecan Street to Cele Road starting with the one-lane bridge closest to Pecan St. 

Throughout the construction, the roadway will remain open with a north and southbound lane of traffic at all times. 

The project will begin in early 2017 with construction scheduled for 20 months.

Proposed improvements include:
-Repairing all bridges from Pecan Street to Cele Road starting with the one-lane bridge near Pecan.
-Expanding road from two to four lanes.
-Adding turn lanes and shoulders
-Improved drainage

The project will begin in early 2017 with construction scheduled for 20 months. 

Project Background

Project Engineer: LJA Engineering

Construction Contractor: TBD

Map:    GIS map project number 56.

Weiss Lane was an approved 2014 bond project which allowed for a reconstruction to the existing two lane section and incorporate shoulders and turn lanes at major intersections.

This project is via a cost-sharing safety project with Travis County bond funds ($6.73 million) previously approved by county voters to reconstruct the current roadway with turn lanes and drainage improvements.  At the November 18, 2014 Council meeting, the city approved an inter-local agreement with Travis County to proceed on improvements to Weiss Lane.

In 2015, the City Council put Weiss Lane back on the ballot for residents to decide if they want a four-lane or a two-lane Weiss Lane.  The 2015 bond was approved by the voters to make a four-lane urban roadway.

With the announcement of the fourth high school along Weiss Lane, this expansion will allow greater access to the new high school. 

Project Schedule and Status
Weiss Lane Rdwy 1016.pngEngineer hired March 10, 2015
Professional services agreement July 14, 2015 and amended in January 2016.
July 2016 - The city completed installation of waterlines for the new high school along Weiss Lane first, and then once roadway acquisition is complete, the city will begin construction of the road. The plan review is complete. The city is coordinating with the county for ongoing design and utility coordination. Appraisals for the right-of-way and easements needed to build the road is underway as of July 2016.
Construction is anticipated in Spring 2017.

Download the Weiss Lane Widening Pfactsheet

For More Information
For a full list of Capital Improvement Projects, information on potential closures and project updates visit  Sign up for the city's weekly e-newsletter, the Key to the City at

Please contact the City of Pflugerville Capital Improvement Program at 512-990-6400 or by email at if you have an additional questions.