In 2014 City Council approved funding for development of a master plan of Lake Pflugerville. After engaging in public open houses and forums with residents, Parks and Recreation Commissioners, and City Council members, and staff, the master plan took shape and was later approved. The master plan includes expansion of existing park facilities, additional utility services, beach expansion and improvement and additional trailheads.

Beach-improvements-phase-1This same year, voters approved the General Obligation bond which included development of Phase 1 of the Lake Pflugerville master plan. Development of a preliminary design report began in 2018 and was approved by City Council in June 2019. Based on further analysis of the existing lake, detailed conceptual facility designs and updated construction cost projections, the report prioritized improvements to the lake that reflected available City funding. Development of an additional trailhead and expansion of specific beach amenities (pictured to the right) were the top improvements identified for Phase 1 development. 

Project Engineer: Halff Associates, Inc.

Construction Contractor: TBD

Map: To view this project on the city's GIS Map  

Biehle-house-phase-1

Budget: $3.6 million 

Benefits

This project was approved by voters in the 2014 Bond election. It will also provide new development to the park based on the approved Lake Pflugerville Master Plan and recommendations from the Lake Pflugerville Preliminary Design Report.

The improvements will alleviate traffic concerns, provide additional trail extensions, expanded park facilities, and new amenities for park users.

Project Schedule and Status

This project is currently in the design development/construction document production phase. The City intends for portions of the improvements to be available for use in the 2020 summer season.

For More Information

Please contact the City of Pflugerville Capital Improvement Program at 512-990-6400 or by email at projects@pflugervilletx.gov if you have an additional questions.