Project Information
Reconstruction of Lynn Cove at Pigeon Forge Raod will include driveway aprons within the right of way, concrete curb and gutter, concrete sidewalk and manhole adjustments
Project Engineer: CP&Y
Construction Contractor: Alpha Paving Industries
Project Schedule and Status
A construction agreement was approved on June 27, 2017 and construction is anticipated to begin in July 2017 and last approximately 45 days. The project was completed in September 2017.