Railroad Avenue Pavement Rehabilitation

Print
Press Enter to show all options, press Tab go to next option

Recent Project News and Information

Letters containing project and logistics information were sent to residents and property owners in July.

Plans and schematics

Project Information

This project is part of the City's Annual Street Maintenance Program and includes rehabilitation and reconstruction of pavement between Wilbarger St. and East Pflugerville Pkwy .  

The reconstruction is scheduled to start in July 2018 to facilitate construction completion before school begins in the fall. .

Project Engineer: Halff Associates 

Construction Contractor: Pro Dirt Service LLC

Map: To view this project on the city's GIS map

Project Schedule and Status

Construction will begin in early July 2018.  The total construction contract was awarded at the June 12 City Council meeting for approximately $760,000. The project is funded from the 2017-2018 Pavement Maintenance Program in the General Fund.

For more information

Please contact the City of Pflugerville Capital Improvement Program at 512-990-6400 or by email at projects@pflugervilletx.gov if you have an additional questions.