Stone Hill Park - 1124 Town Center Drive

Print
Press Enter to show all options, press Tab go to next option
futurestonehillpark

Click here to View the Stone Hill Park Page.

The information below details the park's creation.

Project Information

Stone Hill Park was funded by the November 2014 Bond Election. The Stone Hill park was previously planned as part of the Trails Master Plan & Undeveloped Parks Study that was completed by RVi in July of 2014.

The City engaged MWM DesignGroup for the design of the Stone Hill Project. The initial Scope of Work was to provide a Preliminary Design Report (PDR) that looks at the project sites to identify opportunities and constraints (environmental, historical, cultural, etc), evaluates the previously completed Master Plans to fully vet the proposed amenities and provides updated preliminary designs and cost estimates.

Project Engineer: MWM Design Group

Construction Contractor: The Barr Company AIA

Budget

Funding was from the 2014 Parks bond that was approved by the voters for undeveloped parkland and a contribution of parkland dedication funds from the Mansions at Stone Hill Apartments. The overall budget for Stone Hill Park was approximately $2.2 million.

Project Schedule and Status

Construction is complete.

For More Information

Please contact the City of Pflugerville Capital Improvement Program at 512-990-6400 or by email at projects@pflugervilletx.gov if you have an additional questions.