Kennemer Pavement Overlay

Print
Press Enter to show all options, press Tab go to next option

Project Information

This project is part of the City’s Annual Street Maintenance Program and will provide for pavement resurfacing (asphalt overlay) of Kennemer Dr. with pavement repairs as needed.  The repairs and overlay are planned in 2 phases.

Project Engineer: K. Friese & Associates

Construction Contractor: Alpha Paving

Map: To view this project on the city's GIS map.

Benefits

Asphalt Resurfacing and Overlay is a type of street repair that generally consists of the following steps:

  • Grinding off selected areas of old asphalt either along the curb or within the street 
  • Patching any pot holes or badly deteriorated areas 
  • Placing and compacting hot mix asphalt pavement 
  • Adjusting any street hardware (manhole frames, catch basin frames) to the new grade of the asphalt and completing any restoration of adjacent properties 

By installing a new layer of asphalt over the existing pavement, the City will be able to extend the pavement’s lifespan.

DSCN1279
DSCN1283
DSCN1285
DSCN1286
DSCN1288

Project Schedule and Status

This project started construction in October 2016 and was completed in December 2016.

Kennemer 1016

For More Information

Please contact the City of Pflugerville Capital Improvement Program at 512-990-6400 or by email at projects@pflugervilletx.gov if you have an additional questions.