Project Schedule and Status

The project began in early 2017 with construction and was completed in fall 2019.

Project Information

Throughout the construction, the roadway will remain open with a north and southbound lane of traffic at all times.

This project will widen the roadway from Wilbarger Creek to Cele Rd. from two lanes to four lanes with curb and gutter and drainage improvements. The southernmost section from Wilbarger Creek to East Pecan St. will be reconstructed as a two-lane roadway with shoulders. The project limits are from East Pecan St. to Cele Rd. (3 miles) and include reconstruction of all bridges from Pecan Street to Cele Road starting with the one-lane bridge closest to Pecan St. The project is funded by voter-approved bond funds (City of Pflugerville and Travis County).

Improvements include:

  • Replacing all bridges from Pecan Street to Cele Road starting with the one-lane bridge near Pecan St.
  • Expanding road from two to four lanes
  • Adding turn lanes and shoulders
  • Improved drainage

Project Engineer: LJA Engineering

Construction Contractor: Cash Construction

Map: To view this project on the city's GIS Map  

Funding: Weiss Lane was an approved 2014 bond project which allowed for a reconstruction to the existing two lane section and incorporate shoulders and turn lanes at major intersections.

In 2015, the City Council put Weiss Lane back on the ballot for residents to decide if they want a four-lane or a two-lane Weiss Lane.  The 2015 bond was approved by the voters to make a four-lane urban roadway.

This project is via a cost-sharing safety project with Travis County bond funds ($6.73 million) previously approved by county voters to reconstruct the current roadway with turn lanes and drainage improvements.  At the November 18, 2014 Council meeting, the city approved an inter-local agreement with Travis County to proceed on improvements to Weiss Lane.

 

For More Information

Please contact the City of Pflugerville Capital Improvement Program at 512-990-6400 or by email at projects@pflugervilletx.gov if you have an additional questions.

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer