Water Treatment Plant Membrane Replacement

Print
Press Enter to show all options, press Tab go to next option

Project Information

This project is the final phase of a three phase project spanning three budget years; and will provide for the purchase and installation of the final 5 new cassettes in fiscal year 2016.

Only 20 cassettes were originally installed; and the plant was originally designed and constructed to allow the installation of 25 membrane cassettes. This installation of 5 new cassettes will increase the plant’s treatment capacity to approximately 18 million gallons per day.

Benefits

Benefits include:

  • Increased treatment capacity
  • Extended service life

To view this project on the city's GIS Map, select Project 5.

Project Schedule and Status

Staff anticipate this replacement to be complete by Spring 2016.

For More Information

Please contact the City of Pflugerville Capital Improvement Program at 512-990-6400 or by email at projects@pflugervilletx.gov if you have an additional questions.