Weiss Lane Transmission Main Phase 1

Print
Press Enter to show all options, press Tab go to next option

Project Information

This project will include approximately 1,200 feet of 24-inch water main along Weiss Lane from 1400’ south of Pflugerville Parkway to the Water Treatment Plant and approximately 2,600 feet of 12-inch water main along the north property line of the PfISD high school tract.

A pressure relief valve (PRV) will also be required for service at the south end of the project.

The construction of the new high school requires that this project must be in service by March 2016. This project is being developed concurrently with the Weiss Lane Roadway Reconstruction project.

Project Engineer: Cobb, Fendley & Associates

Construction Contractor: JKB Construction

Benefits

  • Improves water distribution in the service area
  • Enhances reliability for water distribution 
  • Provides new water service for the PfISD High School campus
  • Assists with planning for future demands

To view this project on the city's GIS Map, select Project 48.

WP_20160113_15_05_33_Pro_rsz
WP_20160113_15_42_59_Pro
WP_20160113_15_49_45_Pro
WP_20160114_10_14_42_Pro
WP_20160116_08_57_16_Pro
WP_20160116_10_24_15_Pro
WP_20160116_10_42_58_Pro
WP_20160116_15_49_17_Pro
WP_20160118_11_20_04_Pro
WP_20160118_16_06_19_Pro
WP_20160119_14_12_57_Pro_rsz
WP_20160121_09_25_02_Pro
WP_20160121_09_25_44_Pro_rsz
WP_20160121_09_30_44_Pro

Project Schedule and Status

This project is currently under construction with anticipated completion in Spring 2016.

For More Information

Please contact the City of Pflugerville Capital Improvement Program at 512-990-6400 or by email at projects@pflugervilletx.gov if you have an additional questions.